Urban Dreams

Urban Dreams project has obtained the shoring and excavation permits, and works have been launched.

Site fence, shoring and foundation piles have been completed for the whole project.

The excavation works have reached the first row of anchors. The latter is being installed, injected with pressurized cement and stressed. The dewatering system is being installed. Once operational, the excavation works will continue until reaching the second row of anchors.

The overall percentage of completion of excavation related works is around 70%.